اطلاعیه: سرمایهگذاری ۳۰ میلیارد دلاری صنعت پتروشیمی در منطقه ماهشهر…
مشاوره ، استعلام ، سفارش گیری
021-2587414
جهت رزرو سریع تر با این شماره تماس بگیریدWe show you the path to success
Project Capacity:
3,461,600 tons per yearYear of Launch:
1403Progress Percentage:
100%This project is designed to increase production capacity and improve the quality of petrochemical products in the northern region of the country. Given the strategic location of the complex—close to gas resources and with access to open waters—comprehensive planning has been undertaken for the development of new units.
Main Components of the Plan:
Construction of an olefin unit with an annual production capacity of 1.2 million tons of ethylene and propylene as primary feedstock for downstream industries; development of polymer units including polyethylene and polypropylene production lines with various grades; and modernization of existing units to improve energy efficiency are among the key components of this project.
Competitive Advantages:
Access to regional gas resources
Export capability through northern ports
Use of cutting-edge technologies in unit design
Environmental Measures:
Installation of advanced wastewater treatment systems
Recycling and reuse of chemical solvents
Reduction of greenhouse gas emissions through process optimization
Implementation Timeline:
Phase one includes feasibility studies and basic design over a period of 18 months; phase two involves construction and installation of main equipment over 36 months; and phase three entails gradual commissioning and operation.
Economic Impacts:
Direct employment for 1,200 individuals
Increased value-added within the country’s petrochemical chain
Reduction in imports of polymer products
This project is being carried out with the collaboration of domestic companies and international consultants, and is expected to play a significant role in the industrial development of the region.
Learn about other projects
Progress rate
Duration: 360 days
Project Type: Developmental
Execution Method: EPC
This plan has been designed with the aim of enhancing efficiency and reducing operational costs at the Iranol Petrochemical Complex. Production efficiency will be improved through optimization of chemical processes and upgrading of key equipment. The installation of new catalysts in main reactors will result in a higher conversion rate of raw materials into valuable […]
View Project
Progress rate
Duration: 260 days
Project Type: Constructive
Execution Method: EPC
This project has been designed with the goal of increasing production capacity and improving the quality of petrochemical products in the northern region of the country. Considering the strategic location of this complex near gas resources and access to open waters, a comprehensive plan for developing new units has been prepared. Main Axes of the […]
View Project
Progress rate
Duration: 280 days
Project Type: Developmental
Execution Method: EPC
This plan has been designed to enhance efficiency and reduce operational costs at the Iranol Petrochemical Complex. Production efficiency is improved through optimization of chemical processes and upgrading of key equipment. Installing new catalysts in the main reactors leads to an increased conversion rate of raw materials into high-value products. Reconstruction of heat exchangers and […]
View Project
Progress rate
Duration: 180 days
Project Type: Developmental
Execution Method: EPC
The optimization of the Northern Power Plant encompasses a series of strategic measures aimed at enhancing the performance and efficiency of the facility. Phase One: Thermal Efficiency and Fuel Optimization The first step involves improving fuel consumption and increasing the plant’s thermal efficiency through the installation of advanced heat recovery systems. These systems reclaim lost […]
View Project
Progress rate
Duration: 360 days
Project Type: Constructive
Execution Method: EPS
This plan has been designed with the aim of enhancing efficiency and reducing operational costs at the Iranol Petrochemical Complex. Production efficiency will be improved through optimization of chemical processes and upgrading of key equipment. The installation of new catalysts in main reactors will result in a higher conversion rate of raw materials into valuable […]
View Project
Progress rate
Duration: 150 days
Project Type: Developmental
Execution Method: EPC
This plan has been developed with the aim of enhancing productivity and reducing operational costs at the Iranol petrochemical complex. Production efficiency will be improved through the optimization of chemical processes and the upgrading of key equipment. The installation of new catalysts in the main reactors will lead to an increased conversion rate of raw […]
View Project
Comments
Your Comments
Comments